#2
|
||||
|
||||
|
I've produced a workaround using 4 custom number fields as helper columns and 1 custom text field to hold a custom "Task %".
The YouTube video for this workaround is at How to calculate summary task percent complete when all subtasks are milestones in Microsoft Project - YouTube |
| Tags |
| percent complete, summary tasks |
|
|