fouad.khoury fouad.khoury is offline Custom formula for % completed Windows 10 Custom formula for % completed Office 2019
Novice
Custom formula for % completed
 
Join Date: May 2021
Posts: 1
fouad.khoury is on a distinguished road
Default Custom formula for % completed

Hello,




i noticed that Microsoft Project is not reflecting the accurate percentages of work completions in the following case: (for ex it is showing let's say 40 % progress where the real is should be 30%)

- if a task has duration of 4 days and the task has delayed to 14 days due to delay from customer or for any reason: in this case % completed is still same but after let's say 4 + 14 +5 days it get completed: the total duration now is high and having impact on overall percentage of project due to increase on number of days.


the question is:
how to accommodate this? can we add a custom formula dealing with custom fields?

Kindly advise
Regards,
Fouad
Reply With Quote
  #2  
Old 06-04-2021, 11:49 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Custom formula for % completed Windows 10 Custom formula for % completed Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

How about splitting the task for the period of the delay? So that the delay isn't added to the actual duration which Microsoft Project uses to calculate % complete.
Reply With Quote
  #3  
Old 06-07-2021, 02:47 PM
Guloluseus Guloluseus is offline Custom formula for % completed Windows 7 64bit Custom formula for % completed Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

As above, splitting the task is probably the most acceptable way. If its a client side issue, I Would expect a claim to be made and this would show the problem and effect on overall duration or following tasks.
Project will never give the actual progress, only expected, unless you give it a % complete manually. It doesnt know what is actually happening- thats the planners job!
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
viewing completed goal seek formula katomich Excel 8 03-05-2017 07:14 PM
Custom formula for % completed Custom Formula help jkdiesel Project 13 05-20-2016 08:08 AM
Custom formula for % completed Custom Duration Formula jkdiesel Project 2 05-17-2016 02:04 AM
Custom formula for % completed Custom fields formula fragono Project 2 03-02-2016 11:03 AM
custom formula for duration ericfons Project 0 03-23-2010 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:31 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft