#1
|
|||
|
|||
Assigning different skilled workers to an activity and work amount
Lets say we have a 1000 sf of wall
Worker 1 completes 100 sf per day. So if he worked on it, the duration is: 1000/100 = 10 days And the work is: duration x assigned units = 10 days x 8 hours x 1 worker = 80 worker hours Now lets say we also have a worker 2. And he produces 200 sf of wall per day. If he worked on it, the duration will be 1000/200 = 5 days. And work would be 5 days x 8 hours x 2 worker = 80 worker hours. Is this correct? In other words, here I must say two worker, as if two of worker 1 is working on it, because worker 2 is worth two of worker 1, and this way the total work amount doesn't change right? Because the total work amount MUST be the same for both cases, since the task is the same, which is the 1000 sf of wall, right? |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Fixing Work, % of actual work and Final Date in a task (while assigning resources) | Campelliann | Project | 1 | 01-09-2017 06:15 PM |
How to track resource activity (days, off % work penjding and completed, etc.) | LindaC | Project | 1 | 10-31-2015 11:55 AM |
activity id number showing together with activity name | ketanco | Project | 1 | 04-08-2014 01:27 PM |
Assigning finish date to work with %complete | Guloluseus | Project | 3 | 12-12-2013 10:16 AM |
amount of work | ketanco | Project | 3 | 04-06-2012 08:13 AM |