ketanco ketanco is offline Assigning different skilled workers to an activity and work amount Windows 7 64bit Assigning different skilled workers to an activity and work amount Office 2010 64bit
Expert
Assigning different skilled workers to an activity and work amount
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default Assigning different skilled workers to an activity and work amount

Lets say we have a 1000 sf of wall
Worker 1 completes 100 sf per day.



So if he worked on it, the duration is:
1000/100 = 10 days
And the work is: duration x assigned units = 10 days x 8 hours x 1 worker = 80 worker hours


Now lets say we also have a worker 2. And he produces 200 sf of wall per day. If he worked on it, the duration will be 1000/200 = 5 days.

And work would be 5 days x 8 hours x 2 worker = 80 worker hours. Is this correct? In other words, here I must say two worker, as if two of worker 1 is working on it, because worker 2 is worth two of worker 1, and this way the total work amount doesn't change right? Because the total work amount MUST be the same for both cases, since the task is the same, which is the 1000 sf of wall, right?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixing Work, % of actual work and Final Date in a task (while assigning resources) Campelliann Project 1 01-09-2017 06:15 PM
Assigning different skilled workers to an activity and work amount How to track resource activity (days, off % work penjding and completed, etc.) LindaC Project 1 10-31-2015 11:55 AM
Assigning different skilled workers to an activity and work amount activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
Assigning finish date to work with %complete Guloluseus Project 3 12-12-2013 10:16 AM
amount of work ketanco Project 3 04-06-2012 08:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft