Unit of work
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default Unit of work

Hello,


Work = duration x assigned units


So this is: time x units


Then why does MS project show units of work as hours? Should it not be manhours or workerhours etc...?
Reply With Quote
  #2  
Old 05-15-2021, 12:56 PM
miless2111s miless2111s is offline Unit of work Windows 7 32bit Unit of work Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

It doesn't - it shows assigned units as %. It shows work as hours (or days depending on the option you have chosen).
Thus your formula should be work = time x % and thus the units of duration and work are hours.
Reply With Quote
  #3  
Old 05-15-2021, 09:27 PM
ketanco ketanco is offline Unit of work Windows 7 64bit Unit of work Office 2010 64bit
Expert
Unit of work
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

But the formula for work is

work = duration x assigned units
this is a universal formula
Reply With Quote
  #4  
Old 05-16-2021, 01:14 AM
miless2111s miless2111s is offline Unit of work Windows 7 32bit Unit of work Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

Quote:
Originally Posted by ketanco View Post
But the formula for work is

work = duration x assigned units
this is a universal formula
I fear we may have a mismatch in terms. What do you mean by "assigned units"? In MS Project the assignment of resource at x% of their time is the assignment element. This is measured in % of the resource's time

What are you referring to when you say "assigned unit" which you see as measured in hours?
Reply With Quote
  #5  
Old 05-16-2021, 01:17 AM
ketanco ketanco is offline Unit of work Windows 7 64bit Unit of work Office 2010 64bit
Expert
Unit of work
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

No I mean the universal formula for work.

Work = duration x assigned number of units to the task.

Assigned units can be as 5 men, 6 trucks,

so the work then will be man hours or truck hours etc.....
but why does MS project display it as hours only....
hour is duration. Work is not duration. it is how long certain amount of resource worked for it = duration x assigned units
Reply With Quote
  #6  
Old 05-16-2021, 11:38 PM
miless2111s miless2111s is offline Unit of work Windows 7 32bit Unit of work Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

Quote:
Originally Posted by ketanco View Post
No I mean the universal formula for work.

Work = duration x assigned number of units to the task.

Assigned units can be as 5 men, 6 trucks,

so the work then will be man hours or truck hours etc.....
but why does MS project display it as hours only....
hour is duration. Work is not duration. it is how long certain amount of resource worked for it = duration x assigned units
I am sorry I thought this was a question about MS Project and how it calculates work. I see it is more of a general philosophical point. So in your calculation when you apply 4 people to the task are you assigning them full time or part time? You can't answer this with "well if they were half time it would only be 2 people" as you need to communicate exactly who needs to be working on the task. Hence you need to be able to mark the resources A, B, C and D as 50% of their time. This is what MSP is doing with the allocation of resources (who are assumed to be full time unless marked with a % allocation)
I hope this helps but if this is more of a "MS did it wrong" type comment I suspect it won't.
Regards
Miles
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing Unit from Inch to mm (Word 2013) adbast Word 1 08-10-2019 10:18 AM
Using VLOOKUP to autopopulate Unit Cost without changing old entries robot Excel 4 06-07-2017 07:00 AM
Unit is $, should be € - why is it being changed? Officer_Bierschnitt PowerPoint 2 01-14-2016 03:04 AM
Unit of work [Project 2013] More accuracy with resource, unit %, and cost? cag8f Project 18 01-02-2016 01:51 PM
Unit of work How to keep the citation as one unit without using Ctrl+shift+space? Jamal NUMAN Word 3 04-24-2011 04:48 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft