I would like to highlight 2 weeks as holiday time in my Gantt Chart.
It should look like the typical christmas break that is visual as a grey column. But: I do not want the time to be defined as time off. The highlighted weeks should be considered as working hours. How can I set that up? Thank you in advance. |
#2
|
||||
|
||||
![]()
Take a copy of your Standard calendar and add your 2-week period to this "copy of Standard" calendar using Exceptions.
Then go to your Gantt chart Timeline and change the calendar for Now-working time to "copy of Standard". Your Tasks will have the Standard calendar while your Gantt chart will use the "copy of Standard" calendar with the only difference between the 2 calendars being the 2-week period you want to highlight. |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Changes from Gantt view to Detailed Gantt View | Gary Wynn Miller | Project | 0 | 11-30-2019 04:41 PM |
![]() |
patrickd123 | Project | 1 | 04-24-2015 01:38 PM |
![]() |
raminraiszadeh | Project | 3 | 02-13-2015 01:24 PM |
![]() |
mtbtomo | Project | 5 | 05-14-2014 01:18 PM |
![]() |
Intruder | Project | 5 | 12-20-2012 08:35 AM |