  #1  
Old 05-03-2021, 01:51 AM
AlvaroGN AlvaroGN is offline Change BaseLine Cost, but not time Windows 10 Change BaseLine Cost, but not time Office 2019
Novice
Change BaseLine Cost, but not time
 
Join Date: May 2021
Posts: 2
AlvaroGN is on a distinguished road
Default Change BaseLine Cost, but not time

Hi to everyone!


I would like to know if there is any posiblity to change the cost of the baseline after stablish it, without changing the time of the baseline. (I used fixed cost originally)
My objective is to calculate the earned value. The budget have been changed but not the timeline, and the project is ongoing, so if I create a new baseline the time would be updated too.

thanks!!
Reply With Quote
  #2  
Old 05-04-2021, 07:56 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Change BaseLine Cost, but not time Windows 10 Change BaseLine Cost, but not time Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Have you tried manually overwriting the Baseline Fixed Cost?
Reply With Quote
  #3  
Old 05-04-2021, 10:14 PM
AlvaroGN AlvaroGN is offline Change BaseLine Cost, but not time Windows 10 Change BaseLine Cost, but not time Office 2019
Novice
Change BaseLine Cost, but not time
 
Join Date: May 2021
Posts: 2
AlvaroGN is on a distinguished road
Default

yes I did!
I was wondering if I can create a new baseline without updating the start-finish to current time. Basically create a new baseline with the time I want. (maybe is easier than updating the cost of the baseline)
thanks!
Reply With Quote
  #4  
Old 05-09-2021, 04:13 AM
miless2111s miless2111s is offline Change BaseLine Cost, but not time Windows 7 32bit Change BaseLine Cost, but not time Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

Do you have a copy of the plan with the original timings / progress etc? If so you can take a copy in excel of your current timings / progress etc so that you have it saved. Then reset the timings in the live version of your plans to the original (now you have the original timings and revised costs). Save and overwrite the baseline for both cost and time. Then reset the timings / progress back to the correct data from your excel save. You will have to go through and reset the summary tasks to Auto Schedule as dropping a copy and paste down the whole column will have set them to Manual schedule.
HTH
Reply With Quote
Reply

Tags
baseline fields, costs

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to change colors to time values Ashikido Excel 6 02-01-2021 11:37 AM
Budget Cost - Baseline Cost MAJID Project 0 07-25-2017 05:31 PM
Change computer's time, and all appointment times in Outlook's calendar change TimTDP Outlook 0 03-14-2017 06:56 AM
Change BaseLine Cost, but not time Not all fields are exported to the Baseline Cost Report - Visual Report Rowena Project 3 05-30-2016 04:24 PM
Change BaseLine Cost, but not time Cost resource not taken in real cost pascalbidouille Project 1 08-21-2015 01:25 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft