Old 04-29-2021, 03:10 PM
KBCasey27 KBCasey27 is offline Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks Windows 10 Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks Office 2019
Novice
Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks
 
Join Date: Apr 2021
Posts: 1
KBCasey27 is on a distinguished road
Default Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks

I have a subk, who in their MSP schedule, insist on using the latest contract modification award dates to drive recurring quarterly tasks rather than using the original contract award date. Those mods neither address nor pertain to the quarterly tasks, so my belief is the original project award date should be used to drive those quarterly tasks. This leads to disparate contract deliverable dates. It also fouls the baseline by continually changing the award date.
I cannot find any documentation providing guidance or best practice on which date to use, so I am hoping for some assistance from a PMISP or other scheduling SME.



Thank you.
Reply With Quote
  #2  
Old 04-30-2021, 12:22 AM
miless2111s miless2111s is offline Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks Windows 7 32bit Use Original Award Date or Mod Award Date For Date-Based Recurring Tasks Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

how is it changing the baseline data? That should be fixed unless you're continually overwriting it? In this case consider using some of the other baselines to save the "contracted" baseline and then keep that safe?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Original Date Issues After Forwarding craigb Outlook 0 02-02-2018 02:05 PM
A nagging date/recurring event proof? markg2 Excel 0 09-23-2017 07:50 AM
Microsoft Project 2016 print specific date range stuck on one date martinsalmon Project 1 10-12-2016 11:36 AM
Excel pivot table with a DATE value field for some reason stops at a certain date angie450 Excel Programming 2 08-19-2014 08:50 AM
Original date of a document Tata Word 0 08-10-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:46 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft