MSP baselines 'last saved' dates
 
Join Date: Apr 2021
Posts: 2
ailiasim is on a distinguished road
Default MSP baselines 'last saved' dates


Hi everyone,

When you save a baseline anywhere on baselines 1-10, does the 'last saved' date stamp always appear with the baseline where it was saved?

See the baselines list pic I shared. I just inherited this project scheduled in Microsoft Project. Although date stamps are only with Baseline and Baseline 1, many of the other Baselines (2-10) also have data in them (I mean baselines saved in them). Is this normal?

I am using Microsoft Project Professional 2019. The schedule is accessed from server through Project Web App.
Attached Images
File Type: jpg baselines pic.jpg (199.7 KB, 9 views)
Reply With Quote
  #2  
Old 04-29-2021, 11:50 PM
miless2111s miless2111s is offline MSP baselines 'last saved' dates Windows 7 32bit MSP baselines 'last saved' dates Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

can you check the other elements of the baseline (i.e, duration, work, cost etc)? I have seen people manually copying key data into the baseline columns which doesn't trigger a "baseline save" but does mean they've got baseline start and finish...
Reply With Quote
  #3  
Old 04-30-2021, 12:04 AM
ailiasim ailiasim is offline MSP baselines 'last saved' dates Windows 10 MSP baselines 'last saved' dates Office 2019
Novice
MSP baselines 'last saved' dates
 
Join Date: Apr 2021
Posts: 2
ailiasim is on a distinguished road
Default

Thanks. You are right, this must have been done. The guy before me left some notes that mention pasting data directly into baseline columns.

Thanks a million!
Reply With Quote
  #4  
Old 04-30-2021, 12:15 AM
miless2111s miless2111s is offline MSP baselines 'last saved' dates Windows 7 32bit MSP baselines 'last saved' dates Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

great, glad I could help
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Track changes saved to pdf with only red vertical lines saved peterm Word 4 09-16-2020 07:37 PM
Baselines and status dates - how to use Halesowenmum Project 0 09-19-2018 11:43 PM
Interim Baselines pipmonck1961 Project 2 02-22-2015 11:03 AM
Video not working when saved as .ppt But does when saved as .pptx patientxwolf PowerPoint 5 01-24-2014 02:16 PM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft