#1
|
|||
|
|||
MSP baselines 'last saved' dates
Hi everyone,
When you save a baseline anywhere on baselines 1-10, does the 'last saved' date stamp always appear with the baseline where it was saved? See the baselines list pic I shared. I just inherited this project scheduled in Microsoft Project. Although date stamps are only with Baseline and Baseline 1, many of the other Baselines (2-10) also have data in them (I mean baselines saved in them). Is this normal? I am using Microsoft Project Professional 2019. The schedule is accessed from server through Project Web App. |
#2
|
|||
|
|||
can you check the other elements of the baseline (i.e, duration, work, cost etc)? I have seen people manually copying key data into the baseline columns which doesn't trigger a "baseline save" but does mean they've got baseline start and finish...
|
#3
|
|||
|
|||
Thanks. You are right, this must have been done. The guy before me left some notes that mention pasting data directly into baseline columns.
Thanks a million! |
#4
|
|||
|
|||
great, glad I could help
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Track changes saved to pdf with only red vertical lines saved | peterm | Word | 4 | 09-16-2020 07:37 PM |
Baselines and status dates - how to use | Halesowenmum | Project | 0 | 09-19-2018 11:43 PM |
Interim Baselines | pipmonck1961 | Project | 2 | 02-22-2015 11:03 AM |
Video not working when saved as .ppt But does when saved as .pptx | patientxwolf | PowerPoint | 5 | 01-24-2014 02:16 PM |
Finding Earned Values for Different Baselines in a single project | pratik6312 | Project | 1 | 08-22-2013 11:18 AM |