Hi everyone,

When you save a baseline anywhere on baselines 1-10, does the 'last saved' date stamp always appear with the baseline where it was saved?

See the baselines list pic I shared. I just inherited this project scheduled in Microsoft Project. Although date stamps are only with Baseline and Baseline 1, many of the other Baselines (2-10) also have data in them (I mean baselines saved in them). Is this normal?



I am using Microsoft Project Professional 2019. The schedule is accessed from server through Project Web App.
Attached Images
File Type: jpg baselines pic.jpg (199.7 KB, 9 views)
Reply With Quote
  #2  
Old 04-29-2021, 11:50 PM
miless2111s miless2111s is offline MSP baselines 'last saved' dates Windows 7 32bit MSP baselines 'last saved' dates Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

can you check the other elements of the baseline (i.e, duration, work, cost etc)? I have seen people manually copying key data into the baseline columns which doesn't trigger a "baseline save" but does mean they've got baseline start and finish...
Reply With Quote
  #3  
Old 04-30-2021, 12:04 AM
ailiasim ailiasim is offline MSP baselines 'last saved' dates Windows 10 MSP baselines 'last saved' dates Office 2019
Novice
MSP baselines 'last saved' dates
 
Join Date: Apr 2021
Posts: 2
ailiasim is on a distinguished road
Default

Thanks. You are right, this must have been done. The guy before me left some notes that mention pasting data directly into baseline columns.

Thanks a million!
Reply With Quote
  #4  
Old 04-30-2021, 12:15 AM
miless2111s miless2111s is offline MSP baselines 'last saved' dates Windows 7 32bit MSP baselines 'last saved' dates Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

great, glad I could help
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Track changes saved to pdf with only red vertical lines saved peterm Word 4 09-16-2020 07:37 PM
Baselines and status dates - how to use Halesowenmum Project 0 09-19-2018 11:43 PM
Interim Baselines pipmonck1961 Project 2 02-22-2015 11:03 AM
Video not working when saved as .ppt But does when saved as .pptx patientxwolf PowerPoint 5 01-24-2014 02:16 PM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:02 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft