Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 04-14-2021, 06:04 AM
Miami3005 Miami3005 is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2016
Novice
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?
 
Join Date: Apr 2021
Posts: 2
Miami3005 is on a distinguished road
Default Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?


I am working on adjusting my project plan in MS Project and I need to change the end date on a task without affecting the dates on any of the other tasks?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project to detect task level changes and record a date modified in custom field RJTMEYER Project 3 08-22-2014 07:38 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
How to get project to automatically pull in task dates? Moe Szylak Project 2 04-26-2012 12:37 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft