advillanuevag advillanuevag is offline Project does not change finish date when I duplicate resources Windows 10 Project does not change finish date when I duplicate resources Office 2019
Novice
Project does not change finish date when I duplicate resources
 
Join Date: Apr 2021
Posts: 12
advillanuevag is on a distinguished road
Default Project does not change finish date when I duplicate resources

Hi friends, I am using Microsoft Project 2010 and I have one activity with a duration of 8 days.



I come to happen that I setup the task type to fixed work and then I duplicate the unit of resources assigned to that task, and then Project reduces the task duration to 4 days which is perfect, but the problem is that Project does not change the finish date of the task that is what I was looking for.

What can I do to let Project change the finish date of the task when I duplicate the resource units of the task?
Reply With Quote
  #2  
Old 04-18-2021, 03:34 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Project does not change finish date when I duplicate resources Windows 10 Project does not change finish date when I duplicate resources Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

I've replicated your question in MSP 2010 and the finish date changes with duplicate resources.

Maybe check that you've got "auto-scheduled" task mode for the task and not "manually scheduled".

=jerome
Planners' Place
Reply With Quote
  #3  
Old 04-18-2021, 06:21 PM
advillanuevag advillanuevag is offline Project does not change finish date when I duplicate resources Windows 10 Project does not change finish date when I duplicate resources Office 2019
Novice
Project does not change finish date when I duplicate resources
 
Join Date: Apr 2021
Posts: 12
advillanuevag is on a distinguished road
Default Thanks Jerome

Hi Jerome, I hope you are fine.

Thank you very much for taking the time to write me your reply to my question.

I verified and the task is in auto schedule mode, so I believe it is a Project 2010 bug related to Task type since fixed work task type is not behaving as expected.

Once again, thank you so much for your time and effort to help.

Best regards,

Alberto Villanueva.
Reply With Quote
  #4  
Old 04-19-2021, 02:02 AM
miless2111s miless2111s is offline Project does not change finish date when I duplicate resources Windows 7 32bit Project does not change finish date when I duplicate resources Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

do you have any constraints on the task? - if you have a finish constraint on the task it will behave as you describe.
Regards
Miles

Last edited by miless2111s; 04-19-2021 at 05:04 AM.
Reply With Quote
Reply

Tags
fixed work, resource allocation, task duration

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Is it a bug or not ? Ms Project randomly changes project's tasks resources name when re-open file ? capsule Project 1 11-26-2017 06:45 AM
MS Project 2013 - Manually set up the finish date ??? nicolafusconi Project 1 03-28-2017 08:40 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Project does not change finish date when I duplicate resources Units not properly updated after a Finish Date Change zi1 Project 1 08-04-2012 05:55 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft