Miami3005 Miami3005 is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2016
Novice
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?
 
Join Date: Apr 2021
Posts: 2
Miami3005 is on a distinguished road
Default Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?


I am working on adjusting my project plan in MS Project and I need to change the end date on a task without affecting the dates on any of the other tasks?
Reply With Quote
  #2  
Old 04-14-2021, 08:08 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

assuming this task is linked to other tasks with a FS relationship, change the successor logic to SS.

E.g. if the task you want to extend its finish date is ID3 and its successor is ID4, in the successor column of ID3, enter, 4SS.

=jerome
plannersplace.com
Reply With Quote
  #3  
Old 04-14-2021, 08:39 AM
Miami3005 Miami3005 is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2016
Novice
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks?
 
Join Date: Apr 2021
Posts: 2
Miami3005 is on a distinguished road
Default

It is currently linked with a SS and is linked to a milestone. I am basically trying to push the end date of the task without affecting the other dates in the milestone.
Reply With Quote
  #4  
Old 04-14-2021, 09:03 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 10 Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Only other option that comes to my mind is to break the link to the milestone and apply a "Start No Earlier Than" constraint to the milestone.
Reply With Quote
  #5  
Old 04-19-2021, 02:07 AM
miless2111s miless2111s is offline Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Windows 7 32bit Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

Can you describe the task chain and what you want to change and what needs to be protected? This might allow us to help more?
Do you have the true relationships in the plan (i.e. this can't start until this has finished) rather than time relationships (I'd like to do this and then move onto this)? If you've got the former sort then the plan can tell you the true consequences of change. The latter usually ends up being a pain in the backside as people change their minds about the order they'd like to do things
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project to detect task level changes and record a date modified in custom field RJTMEYER Project 3 08-22-2014 07:38 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
How to get project to automatically pull in task dates? Moe Szylak Project 2 04-26-2012 12:37 PM
Adjusting the end date on a Task in MS Project without affecting the dates on other tasks? MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:40 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft