Old 03-03-2021, 10:34 AM
gflower1 gflower1 is offline Using Material Resources and % Complete to Calculate Cost-to-Date Windows 10 Using Material Resources and % Complete to Calculate Cost-to-Date Office 2016
Novice
Using Material Resources and % Complete to Calculate Cost-to-Date
 
Join Date: Mar 2021
Posts: 1
gflower1 is on a distinguished road
Question Using Material Resources and % Complete to Calculate Cost-to-Date

I have tried (unsuccessfully) several times in the past to get MS Project to align with the workflow/billing process for my company.



We invoice exclusively on prorated material costs-- in our case, how many cubic yards of material was moved from the start of a project to current date.

Normally, (outside of MS Project,) we would either use % Complete of the total material OR (units moved)/(total units).

Since MSP doesn't accept additional decimals in the % Complete field, I assume there would be a way to input however many units of material were moved to date to calculate Cost to Date, but I cannot for the life of me figure it out.

Any help would be greatly appreciated!
Reply With Quote
Reply

Tags
% complete, cost, material

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to number pictures and resources in word for automatic numbering, when adding material between?? Retko Word 1 11-30-2015 10:10 AM
Using Material Resources and % Complete to Calculate Cost-to-Date Different cost rates for resources for different projects linked to the Resource Pool Hanloujohn3515 Project 1 10-31-2015 11:58 AM
Using Material Resources and % Complete to Calculate Cost-to-Date Assigning Resources and percent complete jwindholz2725 Project 1 02-24-2014 10:56 AM
Using Material Resources and % Complete to Calculate Cost-to-Date Cannot type in the cost field of the assign resources dialogue box cldonley Project 1 02-05-2014 07:42 AM
Using Material Resources and % Complete to Calculate Cost-to-Date excel cannot complete this task with available resources - vlookup Taisho Excel 4 01-27-2012 03:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:18 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft