#1
|
|||
|
|||
Automatically assign first available resource of a certain type
I'm an intermediate to advanced Project user.
We have 4 bioreactor stations in our lab. I want to plan an experiment and ask Project to level the experiment to the first available bioreactor. Right now I have defined each bioreactor as an individual resource (1-4) and when I plan an experiment I choose which of the 4 stations it will run on, and then Project can level the schedule if I overbook. But there's no way for me to know which station is available first unless I check manually. Thanks |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Alert me How to assign tasks automatically by some criteria | babysatch | Project | 0 | 07-12-2019 09:55 AM |
resource type not showing | ketanco | Project | 1 | 11-24-2014 03:44 PM |
how to assign a labor resource more than once | ketanco | Project | 3 | 02-11-2014 12:23 PM |
Cannot type in the cost field of the assign resources dialogue box | cldonley | Project | 1 | 02-05-2014 07:42 AM |
Assign resource groups to tasks | jjmclell | Project | 2 | 12-17-2012 04:28 AM |