san X san X is offline ms Project calculates proportional costs incorrectly? Windows 10 ms Project calculates proportional costs incorrectly? Office 2019
Novice
ms Project calculates proportional costs incorrectly?
 
Join Date: Mar 2021
Posts: 1
san X is on a distinguished road
Default ms Project calculates proportional costs incorrectly?

Hi,
I am confused how MS Project calculates proportional costs. I have a task where two ressources do not work same amount of work but they work parallel same time.


In this case I expect different costs (= Kosten) of these ressources or do I have a misunderstanding?
Attached Images
File Type: jpg kosten.jpg (72.7 KB, 6 views)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Formula that calculates cumulative averages lonniepoet Excel 2 02-04-2016 06:31 PM
ms Project calculates proportional costs incorrectly? Microsoft Project Managing Planned / Earned Value & Actual Costs shane_dav71 Project 1 10-06-2014 06:07 PM
ms Project calculates proportional costs incorrectly? Enter a number in a locked equation within a cell that then calculates Carchee Excel 7 06-13-2014 11:11 AM
Image proportional resize not functioning! alexfcm PowerPoint 0 09-27-2012 07:22 AM
Other fonts not proportional spaced like courier> mikeburg Word 0 06-15-2006 02:08 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:24 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft