Building In Substantial Delays
 
Join Date: Jan 2009
Posts: 20
skoz55 is on a distinguished road
Default Building In Substantial Delays

I own a residential construction company and am currently building a schedule for a project to start in a few weeks. My scheduling is typically pretty good; however, ever since COVID hit, it's been a wreck. Ex. I currently have a project that is 2 months behind (9 month build schedule). Due to this, I'm trying to be more realistic about my subs and vendors and plan in A LOT of float time.



What methods do people use to build this much extra time into your Gantt chart? Ex. Do you take a 10-day electrical job and just plugin 20 days? Do you build in extra tasks called "delays" everywhere?

Thanks for your thoughts.
Reply With Quote
Reply

Tags
project days, project management

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Outbox Delays Tr1kk1 Outlook 0 12-11-2018 07:51 PM
How can i show client delays Ronin Project 1 02-16-2018 04:50 PM
VBA Word - Building Block (AutoText) - Array - Replace Text with Specific Building Blocks jc491 Word VBA 7 01-03-2016 10:34 PM
Building blocks show correctly in dropdown, but wrong building block populates in doc wordgirl123 Word 0 10-03-2013 08:30 AM
attachment delays joeboudrie Outlook 0 09-12-2011 04:17 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:42 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft