![]() Hi friends, I am using Microsoft Project 2010 and I have one activity with a duration of 8 days. I come to happen that I setup the task type to fixed work and then I duplicate the unit of resources assigned to that task, and then Project reduces the task duration to 4 days which is perfect, but the problem is that Project does not change the finish date of the task that is what I was looking for. What can I do to let Project change the finish date of the task when I duplicate the resource units of the task? |
Tags |
fixed work, resource allocation, task duration |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Is it a bug or not ? Ms Project randomly changes project's tasks resources name when re-open file ? | capsule | Project | 1 | 11-26-2017 06:45 AM |
MS Project 2013 - Manually set up the finish date ??? | nicolafusconi | Project | 1 | 03-28-2017 08:40 AM |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
![]() |
zi1 | Project | 1 | 08-04-2012 05:55 AM |
MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |