CJ-27 CJ-27 is offline Alternate Resource on Two Overlapping Task Windows 10 Alternate Resource on Two Overlapping Task Office 2019
Novice
Alternate Resource on Two Overlapping Task
 
Join Date: Nov 2020
Posts: 1
CJ-27 is on a distinguished road
Default Alternate Resource on Two Overlapping Task

This is for MS Project 2019.

Hello,

I have a dilemma for a practice question where I need to use levelling to alternate two resources working on the same two overlapping tasks that are fixed work. For example, the two tasks are Task A and Task B with Resource 1 and Resource 2 assigned to both tasks. Task A and B both start and finish in the same time frame.

I need Resource 1 to work 100% of the time on Task A on Day 1 while Resource 2 shows working 0 hours on Task A on Day 1 in the Resouce Usage. Resource 2 will work 100% of the time on Day 1 on Task B while Resource 1 will show working 0 hours on Task B on Day 1 in the Resource Usage.

This alternates on Day 2 where Resource 1 now works on Task B 100% of the time but Resource 2 shows working 0 hours on Task B on Day 2 in the Resource Usage. Resource 2 will work on Task A for 100% of the time while Resource 1 will show working 0 hours on Day 2 on Task A in the Resource Usage.

Again, I must create the condition where when I press the levelling on the two selected tasks, it will come out having the two resources alternating between the two tasks.

This is a tricky question. I am wondering if anyone has done this before and can offer some help.

Thanks for reading and especially appreciate any insight into this.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Alternate Resource on Two Overlapping Task Task filter for a resource view: is it possible? codeghi Project 1 01-10-2016 06:25 PM
Resource allocation with two overlapping tasks JBlack2275 Project 1 03-03-2014 05:16 AM
Alternate Resource on Two Overlapping Task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Alternate Resource on Two Overlapping Task Two resource sheet for one task zapco76 Project 1 11-20-2012 05:43 AM
I am unsure I assigned a task out to a resource. jsteczak Project 3 10-05-2012 04:41 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:44 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft