#1
|
|||
|
|||
|
You would think so but I think there is something wrong with my formatting. when I change the finish date, it will move the other dates so somewhere I must have things set that way. Also, when it shifts the tasks, it doesn't shift them in with the same date spacing. Some tasks get moved way up.
I am taking over another PM's project file so I am trying to fix this file rather than create a new one from scratch. Large Project. Thank you for the reply. |
|
#2
|
|||
|
|||
|
Ok, if the start dates is actualized as indeed started and you are only updating the finish date, and your successors are linked finish to start they should indeed move the same duration as the driving predecessors 'push', this is assuming you are accounting for the work days on your assigned calendar. Of course days will be added to your successors to account for weekends if you are using a 5 day calendar.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Importing schedule into another schedule and keeping the links | abby1428 | Project | 0 | 03-16-2018 04:21 PM |
| Assigning equipment | Kestrel_91 | Project | 1 | 07-26-2017 11:30 AM |
| Email intermittantly not alerting on arrival | fogyreef | Outlook | 0 | 01-23-2016 08:28 AM |
inserting someone elses schedule dates for comparison
|
ketanco | Project | 5 | 10-30-2014 02:26 PM |
Managing equipment and person operating equipment
|
ProfessorGilligan1 | Project | 1 | 04-12-2012 12:29 PM |