#1
|
|||
|
|||
|
Is there any way to remove resource calendars prior to saving as an xml, or prevent a calendar from being created for every resource created?
I'm a Primavera P6 Scheduler and translate MS Project files to P6 on a daily basis, the challenge is since every resource in MSP inherits its own calendar I often have 150+ resource calendars to remove from the xml in Notepad++ prior to importing to P6. Just curious if they can be removed prior to saving to xml. Thanks |
| Tags |
| p6, resource calendars |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Resource Reports not showing Sub project Resource group hours
|
RichB | Project | 3 | 02-24-2017 08:55 AM |
| Public folders calendars disappearing from 'Other Calendars' | rstevenson@gmx.co.uk | Outlook | 0 | 10-09-2015 07:39 AM |
| Managing Resource Individual Calendars | JvdP | Project | 2 | 07-21-2015 12:18 PM |
Resource assignment with resource calendars
|
joday48 | Project | 6 | 08-19-2014 05:49 AM |
| Resource Calendars | caz46 | Project | 0 | 02-12-2011 05:31 AM |