decole decole is offline Project reverts to 8 hours for first working day with a 9 hour calendar Windows 10 Project reverts to 8 hours for first working day with a 9 hour calendar Office 2019
Novice
Project reverts to 8 hours for first working day with a 9 hour calendar
 
Join Date: Sep 2020
Posts: 1
decole is on a distinguished road
Default Project reverts to 8 hours for first working day with a 9 hour calendar

I have started a new programme and changed the calendar to a 9 hour working day. However, Project shows the first working day as 8 hours with the remainder as 9. If I change the hours on the resource usage sheet from 8 to 9 the Gantt chart then shows a duration of 0.89 days Can anyone help with this?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Calendar not working Adamadament Project 0 09-11-2018 12:47 AM
Microsoft Project Extened Working Hours with overtime faomari Project 0 08-15-2017 06:10 AM
Project Calendar - working days have varying hours BarryB Project 1 11-30-2016 07:36 AM
Project reverts to 8 hours for first working day with a 9 hour calendar 24 hour task calendar doesn't show a day?? benl Project 3 12-31-2015 02:55 PM
Project reverts to 8 hours for first working day with a 9 hour calendar calendar -reduced working hours pm_newbie Project 7 01-17-2012 10:34 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:49 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft