#1
|
|||
|
|||
Help with Resource Allocation in MS Project
Hello,
I need help with Project. I am creating a go-live schedule and want to use a resource only once a week and want project to tell me if i am over allocating them. Each task is for 4 hrs and i changed the resource to 10% thinking if assign it to another task the same week it would flag, however, project is using a resource 10% for each task. I am attaching an example Project File. Would appreciate if someone could guide me here. Thanks, B |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project 2013 Resource Allocation Problem | tjbd32 | Project | 0 | 09-20-2018 12:20 PM |
Resource allocation for teams | Richard N | Project | 1 | 11-28-2016 02:33 PM |
MSP 2010 Resource Allocation | smudgepost | Project | 1 | 05-24-2014 12:41 PM |
Resource Allocation | OTPM | Project | 7 | 10-05-2012 03:40 AM |
Allocation of resource | Tray | Project | 3 | 06-01-2012 03:09 AM |