Master/subproject linked tasks - not linking to start date
I have a master project with about 8 sub-projects, from contractors. I am linking the sub-contractor schedules together (ie from contractor A -> contractor B tasks) to follow actual workflow.
It has been working, until I noticed that additional "ghost" lines are being inserted into each sub project as I link them together. That didn't seem to be an issue, until I noticed that the start date of tasks within each sub-project (and therefore showing up in the master project) aren't updating - just staying at the sub-project's "project start date". This seems bizarre...and I don't understand why it's only affecting some, not all lines. It obviously completely breaks the utility of the master project, if I can't link these tasks together and have them update accordingly this whole thing is useless unfortunately. |
#2
|
|||
|
|||
I did this and it didn't generate ghost lines. Did you drag the projects into the "Master" project, or did you ask to insert from the menu?
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Tasks cannot be linked | Patrick Geers | Project | 1 | 03-06-2019 01:33 PM |
Project task numbering changed after linking item in subproject to m aster project | rrs_2017 | Project | 0 | 09-06-2017 06:07 AM |
Insert SubProject after Task x? (Linking ConsolidateProjects to Task) | surumadurum | Project | 1 | 04-05-2016 06:09 AM |
MS Project Master Plan remebers old version of subproject | Sisse.hee | Project | 1 | 01-22-2014 09:03 AM |
PowerPoint Master - 50 LINKED slides - SLOW Update | salfonsi | PowerPoint | 0 | 09-27-2008 02:55 PM |