Project Schedule with multiple calendars
I am working a schedule that have multiple calendars including standard - 5x8's (40hrs per week), & 6x12's (72hrs per week) schedule.
The beginning of the project, workers will be working on the standard schedule and the remaining of the project, they will be working on the 6x12's schedule. I have created the new project 6x12's schedule and was able to assign these calendars to each task, but the "Work" hours were not calculated properly. Example, I have 2 units of one resource for 2 days during the 6x12's schedule, but the "Work" column is still calculating the hours based on Standard schedule which will show 2 units x 8 hours/day x 2 days = 32 hrs instead of 48 hrs. Any advise to correct this? |
#2
|
|||
|
|||
If the 5*8 calendar was created first, chances are that it is the default and resources are copying from that. That would mean that they can only work 8 hrs for 5 days, as thats their limit.
May be worth setting all resources to 24hr working, as this then allows them to use any imposed calendar. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Need to schedule a project based on end date | lostsoul | Project | 3 | 10-04-2016 01:17 PM |
Error occurred, when I went to open a MS Project schedule. | HermannBaumgartner | Project | 1 | 10-29-2014 10:58 AM |
Question about tasks on critical path in MS Project schedule (with a twist) | SomewhereinTX | Project | 7 | 01-06-2014 03:07 PM |
I can't figure out how to get Project 2010 to automatically rebalance my schedule | jackofnothing | Project | 0 | 10-23-2011 04:04 PM |
Powerpoint project schedule | L J Keane | Project | 0 | 09-14-2010 01:24 AM |