Default task2 with unknown start date and duration

how do you create such task but you know it is a successor of task1



thanks
Reply With Quote
  #2  
Old 05-02-2020, 06:52 PM
badmullah badmullah is offline task2 with unknown start date and duration Windows 10 task2 with unknown start date and duration Office 2019
Novice
task2 with unknown start date and duration
 
Join Date: May 2020
Posts: 3
badmullah is on a distinguished road
Default

to rephrase my question

if a task takes 4-7 days 4 best case scenario and 7 the pessimistic case , can this uncertainty be shown when defining the task in MS project ? if so how is this done?

thanks
Reply With Quote
  #3  
Old 05-08-2020, 02:02 AM
Guloluseus Guloluseus is offline task2 with unknown start date and duration Windows 7 64bit task2 with unknown start date and duration Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

The same way any programme that has risk in in it is developed- you take a best guess. Link from task 1 to task 2 to determine the earliest start date, then put a duration for task 2. you can, if you have time and motivation, do a set of programmes showing pessimistic, optimistic and realistic views, but I've never seen a point to it.
Start dates will vary as you update a programme to reflect actual progress, so the risk will be lessened as time goes by.
Generally, risk bars can be inserted in the programme- either one bar to represent realistic risk at the end of the programme, a succession of bars at the end of each section, or a bar for every task where there is a high risk. In this case you can filter to show risk bars, then set to max or 0 to get best and worst cases.
For me, a reasonable estimate with risk bars will give you as good as you are going to get. Experience is essential to gauging risk, and is the only real way of getting something that will work.
Generally, using Time Risk Allocation within tasks will give you something that will work. In cases where tasks are subject to delays beyond your control, you will never be able to give accurate forecasts, but can give fairly accurate overall completion dates.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project - Start/end and duration. 4shome Project 1 01-15-2015 06:31 PM
task2 with unknown start date and duration Fixed end but variable start (and duration) meileetan Project 3 08-22-2014 06:54 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
task2 with unknown start date and duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
task2 with unknown start date and duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft