Total float not calculating correctly
Hello- I have a problem with the total float not showing correctly. I have activity47 which is completing on 13MAY2022 which will be a predecessor to activity 6 ( meaning first activity 47 will complete and then activity 6 will follow). My acitivity 6 can ONLY start on 18MAY2022. I want the activity 6 so start on 18MAY 2022, so that the total float between activity 47 & 6 will be 3 days. I put a finish no later than constraint of 18MAY2022, so that the float is correct, but the date is still 13MAY 2022. I need to have both the start date to be 18MAY2022 so that the float will be 3 days. But when i force the date to be 18MAY 2022, the float becomes 0. so the project is not calculating the float correctly?? or am i missing something?? |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Calculating Total Hours & Minutes Worked | aaghd72 | Excel | 2 | 04-13-2019 03:32 AM |
Total float in GANTT incorrect for summary task | projman | Project | 2 | 02-24-2017 08:54 AM |
Negative total float | loukas | Project | 2 | 11-29-2015 10:38 AM |
Countif function not calculating correctly | MoranGail | Excel | 1 | 07-09-2014 05:50 AM |
MS Project not calculating earned value correctly | mtbtomo | Project | 1 | 10-23-2013 06:49 AM |