brandon17 brandon17 is offline Identify Active Predecessor Windows 10 Identify Active Predecessor Office 2010
Novice
Identify Active Predecessor
 
Join Date: Apr 2020
Posts: 1
brandon17 is on a distinguished road
Default Identify Active Predecessor

Hi,

I am new to ms project and I am creating a timeline, I was hoping there was a way to easily identify what predecessor is driving the schedule when there are multiple predecessors on one task.
eg.


36SS,24FS+4 wks,35SS

It would bold, or underline or someway show that the one task is driving the schedule and the others are not.

Thanks in advance!!
Reply With Quote
  #2  
Old 05-02-2020, 04:48 PM
Guloluseus Guloluseus is offline Identify Active Predecessor Windows 7 64bit Identify Active Predecessor Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Not completely sure what you are trying to achieve - whether its showing others the driver, seeing for yourself, or something else?
Probably easiest just to show a critical path view, although obviously this would only give you critical tasks. I suspect this would be enough, as any live programme will change with progress, and the driver may often change.
Reply With Quote
  #3  
Old 10-09-2020, 07:35 AM
Snoboy Snoboy is offline Identify Active Predecessor Windows 10 Identify Active Predecessor Office 2016
Novice
 
Join Date: Oct 2020
Location: Phoenix, AZ
Posts: 7
Snoboy is on a distinguished road
Default

I wish this was possible also, I am a P6 user and the driving predecessor is always indicated which makes tracing the driving logic much easier. I am not aware of any means to show this in MSP...but will watch this thread just in case!
Reply With Quote
  #4  
Old 10-15-2020, 07:52 AM
Snoboy Snoboy is offline Identify Active Predecessor Windows 10 Identify Active Predecessor Office 2016
Novice
 
Join Date: Oct 2020
Location: Phoenix, AZ
Posts: 7
Snoboy is on a distinguished road
Default

Ok, select the task you are trying to identify its driving predecessor, by clicking the 'Task' tab, 'Tasks' group, 'Inspect' dropdown, 'Inspect Task', a box will appear on the left side of your screen, the driving predecessor will be noted there, its also a link so by clicking on that predecessor you will jump to that task.
I wish there was a column for this when in the 'Predecessor' tab in the Task Information indicating the driver but as far as I know there isn't, but this is a method to determine the actual driving pred.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Identify Active Predecessor Predecessor and successor on different calendar Seftonbarn Project 2 03-17-2017 04:50 AM
Looking to add other fields to predecessor tab. rickjames8 Project 3 03-09-2017 09:46 AM
Identify Active Predecessor Predecessor not considered? Puddlerunna Project 9 09-10-2014 08:13 AM
using a predecessor twice ketanco Project 2 03-07-2014 04:52 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft