Total float not calculating correctly
Hello- I have a problem with the total float not showing correctly. I have activity47 which is completing on 13MAY2022 which will be a predecessor to activity 6 ( meaning first activity 47 will complete and then activity 6 will follow). My acitivity 6 can ONLY start on 18MAY2022. I want the activity 6 so start on 18MAY 2022, so that the total float between activity 47 & 6 will be 3 days. I put a finish no later than constraint of 18MAY2022, so that the float is correct, but the date is still 13MAY 2022. I need to have both the start date to be 18MAY2022 so that the float will be 3 days.
But when i force the date to be 18MAY 2022, the float becomes 0. so the project is not calculating the float correctly?? or am i missing something??
|