#1
|
|||
|
|||
![]()
I am preparing a schedule on Project and have the following relationships between certain tasks:
Task 1 will run fully for 198 days Task 2 will take 150 to complete but will start 3 days after Task 1 and cannot finish until 3 days after task 1. The only way I can think to do this is to split task 2 and drag the split bar to the required start time, but Project won't accept this. Any ideas or suggestions would be gratefully received. |
![]() |