I am preparing a schedule on Project and have the following relationships between certain tasks:
Task 1 will run fully for 198 days
Task 2 will take 150 to complete but will start 3 days after Task 1 and cannot finish until 3 days after task 1.

The only way I can think to do this is to split task 2 and drag the split bar to the required start time, but Project won't accept this.

Any ideas or suggestions would be gratefully received.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Scheduling question mayachen1@gmail.com Project 4 05-06-2017 03:32 PM
Question about leveling a project..... sssb2000 Project 3 02-05-2015 12:11 PM
Project scheduling question How to help - Project 2007 - Scheduling tasks during specific windows of opportunity apexian Project 1 07-12-2013 05:16 AM
Scheduling conflicts in MS Project Antares Project 1 01-24-2012 06:36 AM
Project scheduling question New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft