We are having multiple projects running at the moment and they are all linked to the Resource Pool. The problem is whenever I unlink a project from the pool, following the steps (break the link on the Pool and change the setting on the Sharer file, save both Resource Pool file and the Sharer file), next time when I open the Pool, the link of the Sharer still appears, which is very frustrating as I have to add and remove subprojects very often. Any advice please? Thanks, Jackie |
|