Old 07-30-2019, 01:14 AM
NickEccles NickEccles is offline Supplier task allocation based on Units rather than Work (time) Windows 10 Supplier task allocation based on Units rather than Work (time) Office 2019
Novice
Supplier task allocation based on Units rather than Work (time)
 
Join Date: Jul 2019
Posts: 1
NickEccles is on a distinguished road
Default Supplier task allocation based on Units rather than Work (time)

I have a plan that was a large number of tasks of which I can plan & track resource allocation. However I also have suppliers that we send items to for special work, they have a capacity of how many items they can be processing at anyone time and I'd like to be able to track and highlight any over allocation in a similar way I would to resources using work.



I know I could decided on a Unit of work (number hours per item etc) and use resource allocation but this has a few flaws - including when reporting to our management question why we are tracking suppliers hours!

the only other way I have thought of is using custom fields, export to Excel and highlight it that way? I'm just trying to avoid that as I've just got the organisation to look at using Project rather than excel spreadsheets as it is much more fit for purpose to tracking progress, rebaselining etc.

Has anyone else tried anything similar or have another suggestion ?

Thanks
Nick.
Reply With Quote
Reply

Tags
allocation, resource, supplier

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculating the duration of a task based on work rate Rida Project 0 04-26-2018 03:55 AM
Supplier task allocation based on Units rather than Work (time) Units worked per time period carmang Excel 4 07-24-2014 08:24 AM
Supplier task allocation based on Units rather than Work (time) Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Supplier task allocation based on Units rather than Work (time) Task allocation by priority dlowrey Excel Programming 3 06-18-2012 07:24 PM
Allocation of task in certain period of time mati2 Project 1 02-25-2012 07:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft