Old 07-13-2019, 12:41 AM
buchel buchel is offline How to make same tasknames in different summary tasks distinguishable Mac OS X How to make same tasknames in different summary tasks distinguishable Office 2019
Novice
How to make same tasknames in different summary tasks distinguishable
 
Join Date: Jul 2019
Posts: 2
buchel is on a distinguished road
Default How to make same tasknames in different summary tasks distinguishable

Hi, I have 100 summary tasks all made up by the same 5 subtasks.
E.g.
Ingest
Edit
Review
Export




The summery tasks have different names, the subtasknames are repeating.
In Gantt chart and Any other table I can add the summary task name column. But in team planner I do not know which task belongs to which summary task.
Is there a best practice for bulk rename many tasks?
Or do you have any other idea?
Regards Björn
Reply With Quote
  #2  
Old 08-14-2019, 09:04 AM
TerranceM TerranceM is offline How to make same tasknames in different summary tasks distinguishable Windows 10 How to make same tasknames in different summary tasks distinguishable Office 2016
Novice
 
Join Date: Jul 2019
Location: USA
Posts: 6
TerranceM is on a distinguished road
Default

If this si about a field that exists in Task Information, what you have to do is select the tasks, then click the task information button on the task ribbon. The form "Multiple task information" comes up and you can enter one value for all of the selected tasks.
Reply With Quote
  #3  
Old 08-16-2019, 01:31 AM
buchel buchel is offline How to make same tasknames in different summary tasks distinguishable Mac OS X How to make same tasknames in different summary tasks distinguishable Office 2019
Novice
How to make same tasknames in different summary tasks distinguishable
 
Join Date: Jul 2019
Posts: 2
buchel is on a distinguished road
Default

Hi Terrance,
thanks for your reply, I guess i did not explain it the right way. I will give you a simple example.

We want to build three tables.
First we set up the workflow for one table: (Boldt is the summary task)

build table
leg1
leg2
leg3
leg4
plate
finish

Then we copy the summary task and rename every summary task:

build table 1
leg1
leg2
leg3
leg4
plate
finish

build table 2
leg1
leg2
leg3
leg4
plate
finish

build table 3
leg1
leg2
leg3
leg4
plate
finish

In Gantt view or in the different table views we can show the column "summary task name" which helps to differentiate the subtasks.
But e.g. in team planner I can not see which "leg1" task is meant. All of them look the same.

With such few subtasks it is not a problem to rename them. But what if I build 100 tables or I have many more subtaks in a summary task?

Maybe there is a better way than renaming every single subtask?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Overallocated resource in Summary tasks - cannot get rid! Halesowenmum Project 1 11-11-2018 06:06 AM
How to calculate summary progress date time on summary tasks Logotip Project 0 05-16-2017 01:18 AM
EVM on summary tasks pascalbidouille Project 3 07-21-2015 12:11 PM
Automatic calculation of summary tasks Puddlerunna Project 1 10-15-2014 03:09 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:45 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft