#1
|
|||
|
|||
project 2013 add a resource which is only available for 1 day per week
Hi,
I have the following problem. When I have a task with a duration of 1 day and I set the start date I get the end date. Now I have a resource who works only 1 day per week (20% available, hope, this is the right place to adjust). When I assign this resource to the task I would expect that the end date is not the same day, but 5 days later than the start date... And in addition. For instance I have a complete and complex project with several tasks. A few weeks later I set the available rate from 20% to 40%. Now I would expect that project automatically recalculate all end dates (and if there are connected set the start dates of the following tasks automatically). I hope you can understand my problem. Thanks. |
Tags |
end date, resource |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project 2013 Resource Allocation Problem | tjbd32 | Project | 0 | 09-20-2018 12:20 PM |
[Project 2013] More accuracy with resource, unit %, and cost? | cag8f | Project | 18 | 01-02-2016 01:51 PM |
import of extended resource info into Project 2013 from Excel | amaken | Project | 1 | 11-29-2015 10:12 AM |
Project 2013 - resource capacity column | and | Project | 3 | 02-11-2015 07:10 AM |
Remove resource name from Gannt Bar in Project Professional 2013? | nick@johansens.eu | Project | 1 | 10-16-2014 05:58 AM |