MS project countdown #error
Dear all,
I created in field text1 the countdown formula: DateDiff("d",Date(),[Finish]) and this works well. I have certain rows not indicating a Finish date and then resulting in Text1 as an #ERROR. I tried to implement an IF function, but below ones are already dissaproved in the formula input field. Anyone an idea how to hide an #ERROR? IIF([FINISH] = , , DateDiff("d",Date()) IIF([Text1] = #ERROR , , DateDiff("d",Date()) |
|