I am currently building a schedule for a construction project. I am assigning resources to task and I am looking to maintain an average crew size. I have "Crew 1" and the max units are 12. I am trying to maintain a bell curve with respect to my man-power. Can anyone help me out or point me in the right direct? Thanks, |
|
![]() |
||||