Call up times in Construction program
Hi There,
I'm wanting to create call up times for items in a program. For example for bathroom cabinets might have a 3 week call up. Is there some way of creating this in the same task line or is it just simpler to create a separate task and link them? |
#2
|
|||
|
|||
Generally speaking it s best to create a task for it. A call off period is a task in itself, and it allows you to adjust periods as and whnen info comes through.
the alternative is to put a lag on the previous task, so if the sequence was order material-- call off period 3 weeks -- arrive on site, you could link "arrive on site" from "order" with a 3 week lag ( xxxfs+15 days) but for me this isnt as good- with a task bar in place, you can see where you are |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project 2003 - Commercial Construction template | Rory Todd | Project | 1 | 05-30-2016 04:27 PM |
New heights of construction! | Ulodesk | Chitchat | 0 | 04-27-2015 09:59 AM |
Call Macro from Input Box String | Paulsh | Word VBA | 1 | 11-01-2011 03:15 AM |
Call Excel from Word | donlincolnmsof | Word | 0 | 10-14-2011 05:02 PM |
Construction Project Presentation | manich1 | PowerPoint | 3 | 04-17-2011 08:29 PM |