milestone report
 
Join Date: Feb 2019
Posts: 1
squeezebox is on a distinguished road
Question milestone report

I don't use MS project 2016 much so please forgive me if this is a stupid / easy question to answer.

The standard reports don't give me what I'm looking for. I've tried creating my own report using filters and custom filters.



Please have a look at the screenshot, showing an example Gantt to the left and my desired report to the right.

It must be possible - but how?

Thanks for your help.
Attached Images
File Type: jpg milestone-report.JPG (78.9 KB, 15 views)
Reply With Quote
  #2  
Old 05-13-2021, 03:02 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline milestone report Windows 10 milestone report Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Add 3 custom fields to your View, say Number 1, Number2 & Text1.

Rename Number1 to Milestone Total and enter the formula IIf([Milestone],1,0) and for summary rows calculations, tick Rollup and select Sum from the dropdown.


Rename Number2 to Completed Milestone and enter the formula IIf([Milestone] And [% Complete]=100,1,0) and for summary rows calculations, tick Rollup and select Sum from the dropdown.


Rename Text1 to Milestone % and enter the formula IIf( [Summary] AND [Milestone Total] > 0, Format( [Completed Milestone] / [Milestone Total], "Percent" ) , 0 ) and for summary rows calculations, tick Use Formula.


The Milestone % column will only calculate progress for tasks that are milestones as shown below.


=jerome
www.plannersplace.com
Reply With Quote
Reply

Tags
milestone, report



Similar Threads
Thread Thread Starter Forum Replies Last Post
Milestone Report in MS Project 2016 is Blank pru Project 1 06-16-2021 02:57 AM
Filename options when saving in Word 2013 - using report number at top of a report ? swayzak Word 1 09-08-2017 08:54 AM
milestone report Not all fields are exported to the Baseline Cost Report - Visual Report Rowena Project 3 05-30-2016 04:24 PM
Automation Process of Schedule Report Output and Report Check Score Card ! ozman86 Word VBA 1 11-19-2014 11:52 PM
milestone report milestone with more than 0 day duration ketanco Project 3 06-16-2014 11:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:51 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft