milestone report
I don't use MS project 2016 much so please forgive me if this is a stupid / easy question to answer.
The standard reports don't give me what I'm looking for. I've tried creating my own report using filters and custom filters. Please have a look at the screenshot, showing an example Gantt to the left and my desired report to the right. It must be possible - but how? Thanks for your help. |
#2
|
||||
|
||||
Add 3 custom fields to your View, say Number 1, Number2 & Text1.
Rename Number1 to Milestone Total and enter the formula IIf([Milestone],1,0) and for summary rows calculations, tick Rollup and select Sum from the dropdown. Rename Number2 to Completed Milestone and enter the formula IIf([Milestone] And [% Complete]=100,1,0) and for summary rows calculations, tick Rollup and select Sum from the dropdown. Rename Text1 to Milestone % and enter the formula IIf( [Summary] AND [Milestone Total] > 0, Format( [Completed Milestone] / [Milestone Total], "Percent" ) , 0 ) and for summary rows calculations, tick Use Formula. The Milestone % column will only calculate progress for tasks that are milestones as shown below. =jerome www.plannersplace.com |
Tags |
milestone, report |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Milestone Report in MS Project 2016 is Blank | pru | Project | 1 | 06-16-2021 02:57 AM |
Filename options when saving in Word 2013 - using report number at top of a report ? | swayzak | Word | 1 | 09-08-2017 08:54 AM |
Not all fields are exported to the Baseline Cost Report - Visual Report | Rowena | Project | 3 | 05-30-2016 04:24 PM |
Automation Process of Schedule Report Output and Report Check Score Card ! | ozman86 | Word VBA | 1 | 11-19-2014 11:52 PM |
milestone with more than 0 day duration | ketanco | Project | 3 | 06-16-2014 11:00 AM |