Old 11-09-2018, 09:57 AM
Halesowenmum Halesowenmum is offline Overallocated resource in Summary tasks - cannot get rid! Windows 7 32bit Overallocated resource in Summary tasks - cannot get rid! Office 2010 32bit
Novice
Overallocated resource in Summary tasks - cannot get rid!
 
Join Date: Oct 2014
Posts: 9
Halesowenmum is on a distinguished road
Default Overallocated resource in Summary tasks - cannot get rid!

Hiya

I've got a project which is all auto scheduled tasks.

Allocation of resources is kind of a moot point due to the nature of what I'm planning out. I've got certain steps in a process that can take (as an example) a minimum of 3 days but could take up to 2 weeks. I'm creating the plan based on the maximum duration of time that a summary task could take.

The sub tasks were all showing as overallocated although I'm only adding the resource names into this 'project plan' to show who would do each of the steps - not to indicate any resource allocation or calculate if they are or aren't overallocated.

However, I went through them all and chose the 'ignore' option so that's the sub tasks sorted out.

But two things indicate further things aren't correct:
1. The summary days durations don't tot up correctly 2. I cannot remove the red man from the summary tasks! The option to ignore on right clicking (or any other) doesn't appear.




What do I need to look at now?
Reply With Quote
  #2  
Old 11-11-2018, 06:06 AM
Halesowenmum Halesowenmum is offline Overallocated resource in Summary tasks - cannot get rid! Windows 7 32bit Overallocated resource in Summary tasks - cannot get rid! Office 2010 32bit
Novice
Overallocated resource in Summary tasks - cannot get rid!
 
Join Date: Oct 2014
Posts: 9
Halesowenmum is on a distinguished road
Default

Can anyone help??
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Overallocated resource NOT showing as Overallocated LizaF Project 0 10-17-2018 03:18 PM
How to calculate summary progress date time on summary tasks Logotip Project 0 05-16-2017 01:18 AM
EVM on summary tasks pascalbidouille Project 3 07-21-2015 12:11 PM
Overallocated resource in Summary tasks - cannot get rid! Resource not being marked as overallocated Tarkara Project 2 06-08-2015 09:03 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:34 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft