SSayan SSayan is offline Baseline Cumulative Work and Cumulative Actual Work not avaialble Windows 7 64bit Baseline Cumulative Work and Cumulative Actual Work not avaialble Office 2013
Novice
Baseline Cumulative Work and Cumulative Actual Work not avaialble
 
Join Date: Sep 2018
Posts: 1
SSayan is on a distinguished road
Default Baseline Cumulative Work and Cumulative Actual Work not avaialble

Hello everyone,

I'm using MS project for my schedule and I'm usually having a pretty standard and simple usage of it I just use the duration and links between task.

However, I decided to go to the next level and get my As built and my project S-Curve.


I found a large number of tutorial on how to do that, however I get stuck when I'm asked to add the following columns to the report:
- Baseline Cumulative Work
- Cumulative Actual Work

I can't find them in the list.
My Actual Work and Baseline Work are available but not the cumulative. I can't find any explanation why.

Could anyone help me with that?

Thanks
Reply With Quote
  #2  
Old 10-11-2018, 01:51 AM
stefano99x stefano99x is offline Baseline Cumulative Work and Cumulative Actual Work not avaialble Windows 7 32bit Baseline Cumulative Work and Cumulative Actual Work not avaialble Office 2016
Novice
 
Join Date: Oct 2018
Posts: 2
stefano99x is on a distinguished road
Default

Hi, go to Reports and click Graph Reports, there you will find what you're searching.

Have a good day
Reply With Quote
Reply

Tags
cumulative, scurve, work

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Baseline Cumulative Work and Cumulative Actual Work not avaialble Updating actual work and work on resource spread sheet Campelliann Project 3 01-31-2017 11:17 AM
Fixing Work, % of actual work and Final Date in a task (while assigning resources) Campelliann Project 1 01-09-2017 06:15 PM
Baseline Cumulative Work and Cumulative Actual Work not avaialble Chart: Cumulative line tays01s Excel 1 02-18-2014 05:03 AM
Baseline Cumulative Work and Cumulative Actual Work not avaialble Formulas for cumulative value and cumulative %? Brotein Excel 1 10-29-2013 05:35 AM
Baseline Cumulative Work and Cumulative Actual Work not avaialble Cumulative numbers/percents using DAX Paul-NYS Excel 1 10-01-2013 08:57 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:29 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft