Half hour added between tasks
Hi guys,
I'm new to Project, but experienced with Primavera (not sure if that's a four letter word around here...). I am trying to create a short project of tasks each taking a whole number of hours taking place one after another. I have set up a calendar to have a solid 8 hours working between 0800 and 1600. Despite this I have tasks starting and ending at half hour points; 1330, 1530 etc. And bafflingly 1630(?!) which surely should not appear with a calendar that only goes between 0800 and 1600. Is there some little tick box somewhere that is effecting this change across my project? Cheers, Maru |
#2
|
|||
|
|||
Did you enter your tasks, enter their durations and then link all tasks together as 'Finish to Start'?
Might look in the Task Information dialog box to see if you have Lag time filled in. |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Form field to automatically be added to header? | razberri | Word VBA | 3 | 02-22-2010 03:48 PM |
Help! All Messages in Web Email deleted when account added to Outlook | UrbanEast | Outlook | 2 | 07-17-2009 09:32 PM |
Why red tasks at last 3 tasks of 21 tasks | Jochen | Project | 2 | 04-13-2009 07:29 AM |
Group tasks | grahamsyuk | Outlook | 0 | 09-03-2007 02:31 AM |
Footer so low on page only top half prints | Renee Hendershott | Word | 1 | 01-22-2006 05:09 PM |