Hi guys,
I'm new to Project, but experienced with Primavera (not sure if that's a four letter word around here...). I am trying to create a short project of tasks each taking a whole number of hours taking place one after another. I have set up a calendar to have a solid 8 hours working between 0800 and 1600. Despite this I have tasks starting and ending at half hour points; 1330, 1530 etc. And bafflingly 1630(?!) which surely should not appear with a calendar that only goes between 0800 and 1600. Is there some little tick box somewhere that is effecting this change across my project? Cheers, Maru |
|
![]() |
||||