Assign resources with different calenars to a task
Project 2010/2013/2016
Project calendar set to 8 hour day Task Paint House 1 week duration Auto Schedule Resource1 standard calendar 8hr day Resource2 new standard calendar 12hr day Using split view Task Form Allocate Resouce1 to task (work 40 hrs) Set task fixed duration Allocate Resource2 (work 57hrs - should be 60hrs by my maths) Change work for Resource2 to 60hrs and get over allocation of that resource Go to Task Usage and work allocated on a daily basis for Resource2 appears as 12.63hr, 12.63hr, 12.63hr, 12.63hr, 9.47hr Change 12hr for each day and over allocation disappears Whilst I would like an explanation I would rather know why project can't calculate the work for Resource2 correctly in the first place Many Thanks |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Assign different resources with different colors to the same task | Shir | Project | 9 | 05-05-2017 12:29 PM |
Multiple resources on one task | joday48 | Project | 2 | 08-01-2014 08:56 AM |
Task types with no Resources assigned | mtaylor | Project | 1 | 05-24-2014 12:37 PM |
Cannot type in the cost field of the assign resources dialogue box | cldonley | Project | 1 | 02-05-2014 07:42 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |