how to split working days on a long period
let's suppose that I have one resource (e.g. Anna) that has a task, starting on june 8th and with deadline on june 22nd. so-> start date = june 8th and end date = june 22nd, it is 10 working days i know that Anna is going use only 1 working days, spend in some way during these two weeks. to trace this information, now I calcoulate that 1 day/10dys is 10%, so I say that the allocation of this resource is 10%. is there an easier way? I would like to say that the available timeframe is from june 8th to june 22nd, but the expected timefor this task is only 1 day. thanks!" |
Tags |
allocation, deadline, rasource |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
In a long numbered list, the period disappears after 100. | ryannah05 | Word | 1 | 12-28-2017 05:55 PM |
Tasks Switch to Non-Working Days on Working Calendar | danelloc | Project | 3 | 10-02-2017 12:38 PM |
long table from mail merge: split + arrange position of splitted parts | Marco | Word VBA | 4 | 03-30-2016 05:15 AM |
Non-Working Days on Gantt | JayTT | Project | 1 | 01-28-2011 05:42 AM |
Rules for when a long word should be split | pjl9 | Word | 1 | 09-28-2010 07:07 AM |