Rida Rida is offline Calculating the duration of a task based on work rate Windows 10 Calculating the duration of a task based on work rate Office 2016
Novice
Calculating the duration of a task based on work rate
 
Join Date: Apr 2018
Posts: 1
Rida is on a distinguished road
Question Calculating the duration of a task based on work rate


Hello,

- we are manufacturing desks in batches.
- every batch has different number of desks
- we schedule our work per batch and not per desk. for example: Task1: Batch 11, 34 desks

is it possible to calculate in ms project the work needed for the task (34 desks) if i know the work needed for the production of one desk?

thank you in advance
Reply With Quote
Reply

Tags
task, work

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculating the duration of a task based on work rate Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Calculating the duration of a task based on work rate Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Calculating the duration of a task based on work rate overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
Calculating the duration of a task based on work rate summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
Calculating the duration of a task based on work rate calculating duration ketanco Project 5 12-15-2011 07:15 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:06 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft