M+B_surveyor M+B_surveyor is offline adding dependencies to part of a split task Windows 10 adding dependencies to part of a split task Office 2013
Novice
adding dependencies to part of a split task
 
Join Date: Mar 2018
Posts: 1
M+B_surveyor is on a distinguished road
Default adding dependencies to part of a split task

I want to split a task, keep the start date fixed and make the start of the second part dependent on the start of a preceding task - how can I do this?



Thanks,

Leslie
Reply With Quote
 

Tags
split task



Similar Threads
Thread Thread Starter Forum Replies Last Post
adding dependencies to part of a split task Manage external task dependencies OTPM Project 8 02-17-2017 09:43 AM
adding dependencies to part of a split task Do not split task on task level Mattias Project 5 02-17-2017 09:36 AM
single task with combine SS and FF dependencies Blobb Project 3 06-04-2014 12:24 PM
Split a task fridos Project 2 05-30-2011 11:19 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft