Old 01-22-2018, 02:47 AM
f_m f_m is offline Date format for task end/milestone in diagram Windows 7 64bit Date format for task end/milestone in diagram Office 2013
Novice
Date format for task end/milestone in diagram
 
Join Date: Jan 2018
Location: Germany
Posts: 4
f_m is on a distinguished road
Default Date format for task end/milestone in diagram


Hi there, I'm new to this forum so please excuse any mistakes I may make with my requests as I'm using the German version of MS Project 2013 and am not familiar with the English MS Project terminology.

Now to my question: I'm trying to display dates in the GANTT diagram in the format DD.MM.YY. For some reason I only get DD.MM and I just can't find where to adjust the date format. Changing it in "File -> Options ... Project view" doesn't change the date format in the GANTT diagram. Can anyone here help me?
Reply With Quote
  #2  
Old 03-15-2018, 02:39 AM
f_m f_m is offline Date format for task end/milestone in diagram Windows 7 64bit Date format for task end/milestone in diagram Office 2013
Novice
Date format for task end/milestone in diagram
 
Join Date: Jan 2018
Location: Germany
Posts: 4
f_m is on a distinguished road
Default

107 views and no ideas?
Reply With Quote
  #3  
Old 03-18-2019, 03:36 AM
f_m f_m is offline Date format for task end/milestone in diagram Windows 7 64bit Date format for task end/milestone in diagram Office 2013
Novice
Date format for task end/milestone in diagram
 
Join Date: Jan 2018
Location: Germany
Posts: 4
f_m is on a distinguished road
Default

412 views and still no answer? Wow...
Reply With Quote
  #4  
Old 03-26-2019, 02:35 AM
Guloluseus Guloluseus is offline Date format for task end/milestone in diagram Windows 7 64bit Date format for task end/milestone in diagram Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Natively, Project wont do this, but there is a work around.
1) set date to dd/mm/yy in preferences (as you have done)
2) Under the "Project) tab,Create a custom field and call it start date, finish date, or whatever dates you are trying to show.
3) in the custom field, click on "formula", then field -> date -> Start/finish or whichever.
4) Format bars (under "Format" tab) and choose the field you created.

this will then show date as dd/mm/yy.
hope that helps
Reply With Quote
  #5  
Old 05-23-2019, 05:17 PM
Murali Narayanan Murali Narayanan is offline Date format for task end/milestone in diagram Windows 10 Date format for task end/milestone in diagram Office 2016
Novice
 
Join Date: May 2019
Posts: 3
Murali Narayanan is on a distinguished road
Default

By Gantt diagram, do you mean the Gantt with the time scale shown in multiple tiers. If yes, then you should be able to right click on the Timescale header, go to the appropriate Tier and select the Label you want. I am able to see dd/mm/yy. However, I do not see dd.mm.yy as an option. May be it comes in German version?
Reply With Quote
  #6  
Old 03-16-2020, 03:37 AM
f_m f_m is offline Date format for task end/milestone in diagram Windows 7 64bit Date format for task end/milestone in diagram Office 2013
Novice
Date format for task end/milestone in diagram
 
Join Date: Jan 2018
Location: Germany
Posts: 4
f_m is on a distinguished road
Default

Shame on me, it's too simple a solution: layout -> bar -> date format ... done.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Copying diagram from excel to power point or word changes name of series in the diagram DrNic Excel 0 02-18-2016 09:08 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Letter date changes when merging with Excel - not the format, the actual date! Smallweed Mail Merge 1 02-07-2014 06:00 PM
Date showing 01/01/84 in Network Diagram - Project 2010 JHBPJF Project 1 05-04-2012 07:52 AM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:45 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft